Norlfok Marine
MARINE & COMMERCIAL DIVING CONTRACTORS
Tel: +353 749 736 037
 
 
CASE STUDIES

SELECT INDUSTRY SECTOR BELOW



Greystones Harbour Development
VT4 Scour Protection
Balfast Harbour Cathodic Protection
Port of Cotonou
Whitebridge Underpinning and Scour Protection
ESB Hydroelectric Station Downstream Gates
River Shannon Weir Booms
Baltic 2
Thanet Offshore Wind
Debris Control Booms
Drinking Water Treatment Plants and Storage Facilities
Limerick Main Drainage Scheme
Dun Laoghaire Harbour
Grand Canal Quay Wall Refurbishment
Kennedy Quay Pile Refurbishment

 

Dun Laoghaire Harbour

Dun Laoghaire Harbour


Contract Value:
N/A
Client: John Sisk
Location: St Michaels Pier Dunlaoghaire Harbour
Duration: 9 Months
Completion Date: June 2007



PROJECT DETAILS:

St. Michaels Pier supports the passenger terminal servicing the HSS fast ferry from Dun Laoghaire harbour to the Port of Holyhead in Wales. Maintenance surveys revealed that the large diameter cast in-situ concrete piles supporting the structure were suffering from severe spalling and corrosion to the reinforcing steel.

Norfolk Marine carried out a comprehensive survey highlighting the piles affected, the extent to which concrete cover was lost and the severity of corrosion to the reinforcing bar, the results of which were evaluated to design an effective repair solution.

A fabric formwork pile repair system was elected as the most cost efficient solution due to ease of installation to the large 1.6m diameter piles. The piles concrete together with the exposed repair was cleaned by using HP water to remove all marine growth and lose material. Spacers were fitted to the cleaned piles and the fabric formwork sock zipped around its circumference and suspended from the pier sought. A micro concrete was then pumped into the formwork.

Fabric formwork is preferable for marine concrete pile repairs as the porous fabric allows the free water in the concrete mix to bleed down to a water cement ratio of 0.4.This gives a significant improvement in strength and durability over concrete placed in conventional shuttering systems.

With design of concrete thickness and a mix design incorporating GGBS and fiber reinforcement giving enhance resistance against the ingress  chloride/ sea salts a long lifespan can be obtained.

Subsequent laboratory testing of concrete samples taken on site at Dun Laoghaire resulted in 28 day compressive strengths of 50N/mm2 and above.

Norfolk Marine liaised closely with the Harbour Master to ensure the entire project was completed safely and with no disruption to the harbour’s ferry schedule. View Location

 
 
Norlfok Marine
Norfolk Marine Ltd, Drumconner House, Drumconner, Mountcharles, Co. Donegal